Author: Mitch Schultz
Large door systems are often one of the last major building elements to be fully resolved.
Unfortunately, that is also one of the biggest reasons projects experience avoidable delays.
In industrial, aviation, mining, defence, logistics, and commercial projects, large door systems require structural coordination, engineering input, manufacturing lead time, and operational planning well before installation begins.
When procurement decisions happen too late, or critical details are missed early, projects can quickly run into redesign, programme delays, cost increases, and installation issues.
Quick Answer
The most common causes of delay in large door projects include:
- Door systems being specified too late
- Structural coordination issues
- Missing operational requirements
- Incorrect opening sizes or tolerances
- Incomplete engineering information
- Delayed approvals or design changes
- Unrealistic manufacturing lead times
- Procurement based on price alone
Most delays are preventable when the door system is considered early alongside the building structure and operational requirements.
Why Large Door Systems Often Become a Bottleneck
Large door systems are not standalone products.
They interact with:
- Structural steel
- Cladding
- Building movement
- Mechanical systems
- Operational access
- Traffic flow
- Wind loading
- Safety requirements
Because of this, they affect multiple trades and project stages.
When coordination is delayed, the impacts spread quickly across the programme.
The Most Common Procurement Mistakes We See
1. Treating the Door as a Late-Stage Purchase
One of the most common issues is assuming the door can simply be selected later.
By the time procurement starts, the project may already have:
- Locked structural geometry
- Finalised openings
- Completed engineering
- Ordered steel
- Set construction sequencing
At that point, resolving door-specific requirements often creates redesign pressure.
Large door systems should be considered during early design coordination, not just before installation.
2. Not Resolving Structural Movement Early
Large openings move.
Deflection, tolerance, and structural movement can significantly affect:
- Track alignment
- Sealing performance
- Door operation
- Long-term reliability
We often see projects where:
- Structural movement allowances were underestimated
- Tolerances were not coordinated
- The structure and door system were designed separately
This can lead to installation delays and operational issues later.
3. Procurement Based Only on Upfront Cost
Lowest upfront price does not always deliver the best project outcome.
Door systems that appear similar on paper may differ significantly in:
- Structural integration
- Wind performance
- Automation systems
- Manufacturing quality
- Maintenance requirements
- Operational lifespan
When procurement focuses only on initial cost, projects can experience:
- Increased maintenance
- Delayed installation
- Reduced reliability
- Operational disruption
- Higher lifecycle costs
4. Missing Operational Requirements
A door system should be designed around how the facility actually operates.
Important questions often missed early include:
- How often will the door cycle daily?
- What vehicle types use the opening?
- Is speed of access important?
- What environmental conditions exist?
- Does the building require thermal or acoustic performance?
- How will emergency access work?
Without this information, the selected system may not suit the actual operational demands.
5. Underestimating Manufacturing Lead Times
Large door systems are typically engineered and manufactured to project-specific requirements.
Lead times can be affected by:
- Opening size
- Structural complexity
- Automation integration
- Custom engineering
- Procurement timing
- Material availability
- Client specific requirements
One of the biggest procurement mistakes is assuming the door system can be delivered within standard construction lead times.
Early engagement helps align manufacturing with the overall programme.
6. Incomplete Information at Tender Stage
Incomplete tender documentation often creates confusion later.
Missing details may include:
- Structural tolerances
- Wind region requirements
- Door operational intent
- Automation specifications
- Compliance requirements
- Service access needs
This can lead to:
- Scope gaps
- Variations
- Delays during shop drawing review
- Re-engineering
Clear documentation early improves procurement clarity and project certainty.
7. Leaving Coordination Until After Steel Is Fabricated
Once structural steel is fabricated, flexibility reduces significantly.
Late changes to:
- Opening sizes
- Support structures
- Tracks
- Clearance requirements
- Load paths
create major programme impacts.
Early coordination between the builder, engineer, and door manufacturer is critical.
What Good Procurement Looks Like
Projects that run smoothly typically resolve door considerations early.
That includes:
- Early structural coordination
- Clear operational requirements
- Site-specific engineering
- Realistic lead time planning
- Defined performance expectations
- Coordination between trades
The earlier these conversations happen, the easier it becomes to avoid downstream issues.
Why Early Collaboration Matters
Large door systems affect more than access.
They influence:
- Structural design
- Programme sequencing
- Safety outcomes
- Operational efficiency
- Building performance
- Long-term maintenance
When project teams collaborate early, procurement becomes far more predictable.
How OpenX Approaches Project Coordination
At OpenX Doors, we work with builders, engineers, architects, and project teams early to help reduce procurement risk and improve coordination outcomes.
This includes:
- Structural integration guidance
- Operational planning support
- Opening coordination
- Wind and performance considerations
- Manufacturing lead time planning
- Installation coordination
Because resolving large door systems early usually leads to smoother projects later.
Most delays in large door projects are not caused by installation itself.
They start much earlier during:
- Design coordination
- Procurement planning
- Structural integration
- Scope definition
The earlier these issues are identified, the easier they are to solve.
If your project includes large openings, specialised operational requirements, or complex structural coordination, early planning can significantly reduce project risk.

Planning a Project With Seriously Big Doors?
If you’re working through industrial, aviation, mining, logistics, or commercial facility design, resolving door requirements early can help reduce redesign, delays, and procurement risk later in the project.
At OpenX Doors, we work alongside project teams to help coordinate large door systems with the structure, operational requirements, and construction program from the outset.